What we found on site
Saturated insulation and a brittle, cracked legacy bitumen membrane were producing recurrent leaks above live production lines, with limited access windows and high rooftop temperatures.
How TEXSA delivered
Works were phased zone-by-zone around plant operations: removal of saturated insulation, screed repair, primer, reinforced liquid PU membrane and UV topcoat. Adhesion and DFT were verified per zone and signed off by the FM team.
Outcome on handover
12,000 m² re-waterproofed with no production downtime, full warranty package and a documented maintenance plan handed over to the operator.
Drag to reveal
Before
AfterSystem data sheet
- System
- Liquid-applied PU membrane with polyester reinforcement and UV-stable topcoat
- Area
- 12,000 m²
- Duration
- 20 weeks
- Sector
- Industrial
- Service
- Roof Rehabilitation
- Location
- Mussafah, Abu Dhabi
- Year
- 2024
- Client
- Confidential — Industrial Operator