Mixed-Use Tower Podium Waterproofing
PROJECT // 03·Commercial·2023

Mixed-Use Tower Podium Waterproofing

Podium and planter waterproofing under landscaped overburden.

ClientConfidential — Developer
LocationAbu Dhabi
Area6,200 m²
Duration10 weeks
ServiceWaterproofing
01 / The challenge

What we found on site

The existing substrate showed extensive deterioration — failed membranes, active leaks, and chloride-laden concrete that compromised long-term performance.

02 / Our approach

How TEXSA delivered

TEXSA mobilised a specialist crew for full strip-out, substrate repair, and reinstatement using pure polyurea + drainage composite. Works were sequenced around live operations with full QA/QC documentation.

03 / The result

Outcome on handover

Podium and planter waterproofing under landscaped overburden. Delivered on programme with a 10-year system warranty and zero post-handover defects to date.
04 / Transformation

Drag to reveal

Mixed-Use Tower Podium Waterproofing — before rehabilitationBefore
Mixed-Use Tower Podium Waterproofing — after rehabilitationAfter
REF_TX03 · Before / AfterAbu Dhabi
05 / Specification

System data sheet

System specificationDATA_SHEET
System
Pure polyurea + drainage composite
Area
6,200 m²
Duration
10 weeks
Sector
Commercial
Service
Waterproofing
Location
Abu Dhabi
Year
2023
Client
Confidential — Developer
07 / Documentation

On-site photography

IMG_01Mixed-Use Tower Podium Waterproofing — photo 1
Mixed-Use Tower Podium Waterproofing — photo 2
Mixed-Use Tower Podium Waterproofing — photo 3
Mixed-Use Tower Podium Waterproofing — photo 4
Mixed-Use Tower Podium Waterproofing — photo 5
Mixed-Use Tower Podium Waterproofing — photo 6
08 / Verified results
6,200 m²
Area delivered
10 weeks
Programme
10 yr
System warranty
0
Post-handover defects